Project Init Date :
2016/04/06
Project Updated : 28-01-2016
PPP Project Info as on 28-04-2025
Project Timeline
RFP DCA sent to department
08-Aug-2017
PPP Cell sent draft RFP DCA and PIM to department.
Revised RFP DCA sent to department
18-Jul-2017
Revised RFP DCA sent to department
Meeting held
28-Jun-2017
Meeting held and PPP Expert attended the meeting.
RFP Document sent to department
20-Mar-2017
Department asked to provide document in soft copy. RFP Document sent to department via email by PPP Associate .
Project Initiated
20-Mar-2017
Project: Integrated Solid Waste Management at Haldwani Cluster (Landfill & Composting Plant)
Department: Nainital Municipal Authority
Project Cost: Rs.0