82 mld STP Project
Project Timeline Documents Print

Peyjal Nigam
82 mld STP Project

Status : Operational
Project Init Date : 2017/03/16
Project Updated : 28-01-2016
PPP Project Info as on 26-04-2024

Project Information

Project Name 82 mld STP Project Project Brief Not Available Department Peyjal Nigam Sector Urban PPP Type Build-Operate-Transfer Contracts Sub-Sector Sewage Collection, Treatment and Disposal System PPP Sub-Type Build-Operate-Transfer (BOT) Annuity Location Haridwar     District Haridwar State Uttarakhand Nodal Authority State Capacity Not Available Project Benefits Not Available

Project Authority

Name of Authority Peyjal Nigam Email Not Available
Name of Contact Person Not Available Phone Not Available
Address Not Available

Project Concessionaire

Name (Concessionaire) HNB Engineers Pvt. Ltd Email Not Available
Contact Person Not Available Phone Not Available
Address Haridwar
Description Not Available
Concession Agreement Signing Date 2017/03/16 Financial Closure Not Available
Concession Duration (Years) 2 Contract Ends 2019/03/16
Construction Start Date (As per Agreement) Not Available Construction Start Date (Actual) Not Available
Construction Completion Date (As per Agreement) Not Available Construction Completion Date (Actual) Not Available
Date of Start of Commercial Operation (As per Agreement) Not Available Date of Start of Commercial Operation (Actual) Not Available
Concession End Date (As per Agreement) Not Available Concession End Date (Actual) Not Available
Capacity Completion Year (As per Agreement) Not Available Capacity Completion Year (Actual) Not Available

Project Costs (Rs. in Crore)

Project Funding Private Partner Estimated Project Cost 273.47
Concession Not Available Project Cost (As per Agreement) 273.47
Grant Type Capital Project Cost (Actual) 273.47