Tourism Development Board
Surkunda Devi Ropeway
(Timeline)
Status :
Implementation
Project Init Date :
2010/01/01
Project Updated : 28-01-2016
PPP Project Info as on 26-01-2021
Project Timeline
Contract Signed with M/s K R Anand (authorized signatory)
09-Apr-2013
Contract Signed with M/s K R Anand (authorized signatory)
Pre bid Meet
31-Jan-2013
Pre bid Meet 05.11.2012
RFQ cum RFP released in newspaper,
16-Oct-2012
RFQ cum RFP released in newspaper,
Project Initiated
16-Oct-2012
Project: Surkunda Devi Ropeway
Department: Tourism Development Board
Project Cost: Rs.15