PWD, Nainital Kosi River Bridge Ramnagar, Nainital(Timeline)
Status : Implementation
Project Init Date : 2011/10/24
Project Updated : 28-01-2016
PPP Project Info as on 18-03-2025
Project Timeline
Meeting held for steering group
03-Feb-2012
Meeting held for steering group
Independent Engineer appointed
21-Oct-2011
Independent Engineer appointed Vasishta Construction Pvt. Ltd, Plot no 23, Rao & Raju colony, Road No 2 Banjara Hills, Hyderabad (AP). Date of start 21.10.2011 to 20.04.2013
Financial Bid opened
09-Aug-2011
Financial Bid opened
RFP evaluation report sent 04 bids were recd all were technical qualified
03-Aug-2011
RFP evaluation report sent
04 bids were recd all were technical qualified
RFP Released
14-Jun-2011
RFP Released
Meeting held
03-Feb-2011
Meeting held
Revised RFP Sent
02-Dec-2010
Revised RFP Sent
EFC Minutes of the Meeting
24-Nov-2010
Minutes of the EFC meeting held under the chaimanship of Principal Secretary (finance) on 24 nov 2010 for proposed bridge over river kosi at Ramnagar in PPP mode. The EFC discussed the two possible options of financing the project VGF and Annuity.